Kintetsu Real Estate and UR Break Ground on Retail-and-Rental-Housing Complex in Front of Nakano Station

Kintetsu Real Estate and UR Break Ground on Retail-and-Rental-Housing Complex in Front of Nakano Station

Kintetsu Real Estate and the Urban Renaissance Agency (UR) began construction in July 2026 of the mixed-use facility (tentative) Nakano 3-chome Hub Facility in Nakano 3-chome, Nakano Ward, Tokyo. Completion is scheduled for the summer of 2029.

The 14-story facility will house retail on the first through third floors and 165 family-oriented rental housing units on the fourth through 14th floors, along with open space that can be used for community exchange and disaster-prevention events.

In the Nakano 3-chome district, the Nakano 3-chome Land Readjustment Project implemented by UR will develop the Nakano Station Toen Plaza and roads on the south side of the north-south passage on the west side of Nakano Station, reorganizing the block. Nakano Ward aims to connect the station-front plaza with residential areas and to form a townscape that harmonizes cultural vibrancy with daily life, and several redevelopment projects are currently underway simultaneously around Nakano Station. As part of this, the opening of the west-side north-south passage and elevated station building, as well as the opening of the Atre Nakano station building, have been announced for December 2026 (see related article: Atre to Open Station Building at Nakano Station).

Major Developments Around Nakano Station

District

Main Development Content

Main Timing

Nakano Station

North-south passage, elevated station building, Atre Nakano

December 2026 service start / opening

Nakano 3-chome

Toen Plaza, retail-and-residential complex

December 2026 (planned Toen Plaza opening) / summer 2029 (planned complex completion)

Nakano 2-chome

Station-front plaza, business, retail, residential

FY2028 completion of south-exit station plaza

Kakoicho

Business, retail, residential, plaza

East area: completed April 2026 / West area: completion scheduled October 2029

Shin-Kitaguchi Ekimae

Redevelopment of the former Nakano Sun Plaza site and surroundings

Completion envisioned in FY2034

Key Facts

  • Project Name: (tentative) Nakano 3-chome Hub Facility
  • Developer: Kintetsu Real Estate Co., Ltd. / Urban Renaissance Agency
  • Location: 3-40 Nakano, Nakano-ku, Tokyo
  • Nearest Station: Three-minute walk from Nakano Station on the JR Chuo Line, JR Sobu Line, and Tokyo Metro Tozai Line
  • Construction Start: July 2026
  • Completion: Summer 2029 (scheduled)
  • Number of Floors: 14F / B1 (reinforced concrete construction, seismic isolation structure)
  • Area: Site area of approximately 728 tsubo (approx. 25,900 sq. ft.) / Gross Floor Area of approximately 5,350 tsubo (approx. 190,400 sq. ft.)
  • Use: Apartment building (165 rental housing units) and retail