The Sankei Building announced on November 18, 2026, that it has decided to invest in Ishikari Renewable Energy Data Center No. 1 GK, which develops and operates the data center Ishikari Renewable Energy Data Center No. 1 in Ishikari, Hokkaido. The investment is scheduled for March 31, 2027.

The facility was completed on March 27, 2026. It has a gross floor area of approximately 3,045 tsubo (approx. 108,400 sq. ft.), a power receiving capacity of 15,000 kW and six sections. All of the electricity it uses is covered by power from renewable energy power plants in Ishikari City. The project began in 2022, with Tokyu Land and Flower Communications handling project management and Agility Asset Advisers handling asset management (see related article: Tokyu Land Completes 100% Renewable Energy Data Center in Ishikari).

The facility began service on August 1, 2026. Within the facility, BroadBand Tower operates its data center base, Ishikari Shinko Site. GMO Internet plans to bring a GPU cloud service base into operation using part of the site within 2026.

In October 2025, The Sankei Building opened OPTAGE Sonezaki Data Center, its first urban data center, in the Higashi-Umeda area of Osaka. For this facility, group company Sankei Building Techno handled the basic design, and Sankei Building Asset Management handled asset management for the TMK. The company plans to accelerate its efforts in the data center field through this investment (see related article: The Sankei Building and Kansai Telecasting Complete OPTAGE Sonezaki Data Center (OC1) in Osaka).

Key Facts

  • Property Name: Ishikari Renewable Energy Data Center No. 1
  • Project Entity: Ishikari Renewable Energy Data Center No. 1 GK
  • Investor (this announcement): The Sankei Building Co., Ltd.
  • Scheduled Investment Date: March 31, 2027
  • Asset Management: Agility Asset Advisers Inc.
  • Project Management: Tokyu Land Corporation / Flower Communications Inc.
  • Location: 722-1 and 722-2 Shinko-Chuo 1-chome, Ishikari, Hokkaido (lot numbers)
  • Completion: March 27, 2026
  • Service Start: August 1, 2026
  • Gross Floor Area: Approximately 3,045 tsubo (approx. 108,400 sq. ft.)
  • Power Receiving Capacity: 15,000 kW
  • Number of Sections: 6
  • Use: Data center