Mitsui Fudosan Starts Phase II of Rebuilding at First LaLaport

Mitsui Fudosan began construction work in November 2026 on the Phase II area of the North Wing rebuilding at Mitsui Shopping Park LaLaport TOKYO-BAY, a retail facility in Funabashi, Chiba Prefecture. Following the Phase I area, which opened in October 2025, the Phase II area is scheduled for completion and opening in summer 2028.
The facility opened in April 1981 as LaLaport Funabashi Shopping Center and was the first LaLaport. Part of the North Wing was temporarily closed in January 2023, and the rebuilding is proceeding in two stages, Phase I and Phase II.
The facility is a five-minute walk from both Minami-Funabashi Station on the JR Keiyo and Musashino lines and Funabashi-Keibajo Station on the Keisei Main Line. The North Wing is a three-story building, and the rebuilding will expand its gross floor area from approximately 29,300 tsubo (approx. 1,042,600 sq. ft.) to approximately 31,200 tsubo (approx. 1,110,200 sq. ft.) and its retail floor area from approximately 13,600 tsubo (approx. 483,900 sq. ft.) to approximately 18,200 tsubo (approx. 647,600 sq. ft.). The Phase II area will house about 200 stores, bringing the total number of stores in the facility to about 600.
At the center of the Phase II area, an indoor Stadium Court will be created by expanding the former central plaza to about three times its previous size. It will be the company's third such installation at its retail facilities, following LaLaport SAKAI (opened in November 2022) and LaLaport ANJO (opened in April 2025). Harbor Street, an outdoor space of about 350 m running through the center of the facility, will be doubled in width, and an artificial turf plaza and a play equipment area will be newly established.
In the Minami-Funabashi area, the retail facility LaLa Terrace TOKYO-BAY, directly connected to JR Minami-Funabashi Station, opened in November 2023, and LaLa arena TOKYO-BAY, a multipurpose arena with a capacity of 10,000, was completed in April 2024. The company said it will work with these facilities to promote community development that takes advantage of sports and entertainment.
Key Facts
- Project Name: Mitsui Shopping Park LaLaport TOKYO-BAY North Wing Redevelopment (Phase II)
- Developer: Mitsui Fudosan Co., Ltd.
- Location: 2-1-1 Hamacho, Funabashi, Chiba Prefecture
- Nearest Station(s): Five-minute walk from Minami-Funabashi Station on the JR Keiyo and Musashino lines / Five-minute walk from Funabashi-Keibajo Station on the Keisei Main Line
- Construction Start: November 2026
- Completion and Opening: Summer 2028 (scheduled)
- Number of Floors: 3F (steel frame construction)
- Area: Gross Floor Area of approximately 31,200 tsubo (approx. 1,110,200 sq. ft.) (before rebuilding: approximately 29,300 tsubo (approx. 1,042,600 sq. ft.)) / Retail floor area of approximately 18,200 tsubo (approx. 647,600 sq. ft.) (before rebuilding: approximately 13,600 tsubo (approx. 483,900 sq. ft.)) (both for the entire North Wing Phase I and Phase II areas)
- Area of Entire Facility: Gross Floor Area of approximately 130,600 tsubo (approx. 4,647,100 sq. ft.) / Retail floor area of approximately 50,300 tsubo (approx. 1,789,800 sq. ft.) (including LaLaport Mitsui Building)
- Number of Stores: Phase I: 96 / Phase II: about 200 (entire facility: about 600)
- Parking: About 7,200 vehicles
- Design: Basic design by Tokyu Architects & Engineers Inc.
- Detailed Design and Supervision: Taisei Corporation
- Construction: Joint venture of Taisei Corporation, Taisei U-Lec and Abe Kensetsu
- Operation and Management: Mitsui Fudosan Retail Management Co., Ltd.
- Phase I Schedule: Construction start in March 2024 / Completion in September 2025 / Opening on October 31, 2025